Solar Utility Contractor
LOCATION
California
NUE Product Solution
SunCase 2025
Market
Commercial Remote Power
Challenge
- In the California high desert at 300MW solar plant
- Power 30 SCADA systems for 3 months before local power was made available.
- Replace portable gasoline generators
Results
- Avoided 30 points of daily refueling of gas generators with zero trips to maintain the Suncases until decommissioning
- Reduced noise and fumes in several high trafficked worker locations
- All units were re-deployable after their initial use
- Mitigated over 50,000lbs of carbon
NUE Product Solution


×